Re-using existing pipework and installing new indoor and outdoor units utilising the Daikin Q series R410 VRV III systems.

Client: LloydsProject Value: £355kProject Period: August 2012 to October 2012

Description

Working in a live environment on a floor by floor basis we replaced the indoor and outdoor AC units. We also installed new emergency lighting throughout the four story building. A new AHU was also installed along with kitchen and toilet extract. A full periodic inspection of the electric installation was also carried out. Fire stopping was also installed throughout.

Works

• New Daikin Q series VRV III units installed • New AHU and Electrical switchgear • Full periodic inspection with category 1&2 rectification • Ductwork modifications to suit • New emergency lighting installation throughout • New Computer room AC systems with run-standby configuration • Fire stopping works throughout